    The foundation forms and rebar are done! There’s 2”foam on the outside walls and the crew did a bit of touch up excavation.

We’re on the south guest patio looking west. There is going to be a curb around the elevator’s floor. That’s what the inner form is for. They drilled holes into the foundation wall and epoxied them into place.

Martin wasn’t sure about how the curb rebar was connected to the foundation walls. So he took this close up of the west side. It turns out that both the top and bottom rebar are connected to the pins (Big rebar!) epoxied into the foundation walls.

Here’s the detail of the north side. You can really see the grey epoxy on this one.