April 2019
25th - 29th - 1st blast preparation and shoot
May 2019
4th - blasting Crawl space under west master and northeast corner of lower level
4th - blasting Propane tank hole
16th - Drilling for the pool blast
17th - Clearing the holes, loading and shooting the pool blast.
June 2019
July 2019
6th - Blast to trim up lower floor south west wall
August 2019
7th - Start of wall forms created
15th - Wall forms almost complete
29th - The Wall forms stripped
September 2019
11th - First mention of The Grotto
19th - Backfill material being brought up
26th - Framers precisely measuring for sill plate placement & Architects rendering
October 2019
3rd - Lower level fill and The Grotto
17th - Garage steel deck started and The Grotto footers poured
November 2019
5th - The Grotto and lower level floor prep
5th - The Grotto and lower level floor pour
December 2019
10th - Framer’s and Doug’s photos before sunrise
12th - Weekly on site and Pool shotcrete complete
19th - Weekly on site and the lower part of the Moment Frame.
30th - Utility Trench final blast and upper level floor complete.